Occupant load is the number of people a space is permitted to hold. It affects many design choices, and it is set by use and area.

Fire Code and Occupant Load

How it is determined

Codes assign an area per person for each type of use. A restaurant dining room, a retail floor and an office all have different figures. The total, divided by the space, sets the maximum number of people.

The count influences exits, corridor widths and washroom requirements.

Mixed uses in one space, such as a cafe with a retail corner, may be assessed under more than one category.

Effects on the design

More occupants may require more exits, wider doors, more washroom fixtures and additional fire protection. A small increase in capacity can trigger a large change.

Designers and our in-house engineering team check this at the start so the layout is realistic.

Fire Code and Occupant LoadPHASE 1Site and leasePHASE 2Design and engineeringPHASE 3BuildPHASE 4OperateBUILD: TRADES ON THE PROJECTElectricalMechanical / HVACPlumbingLow voltage / securityInterior systemsCarpentry / millworkPainting / finishesDoors / hardwareSELF-PERFORMED BY HSM CREWS ON THIS TYPE OF WORK
How HSM delivers this work. Highlighted trades are self-performed by our own crews.

Fire protection systems

Sprinklers, alarms, emergency lighting and exit signs are set by occupancy type and size. Changing the use can require upgrades, even if the physical space is unchanged.

Our team installs electrical, alarm and emergency lighting systems in-house, which keeps the coordination simple.

Alarm devices, door releases and exit signs are tied together, so a single team installing them reduces conflicts.

Common problems

Assembly uses such as restaurants, event rooms and fitness studios often hit load limits. Others forget to account for mezzanines, storage or future growth.

If the design assumes a higher count than the building can support, redesign can be expensive.

What to do

Raise the intended occupant count in your first design meeting and confirm with the authority having jurisdiction where needed. Keep posted capacity signs current.

Our engineers can prepare an occupant load summary that your landlord and reviewers can read quickly.

Questions we hear

Who sets the occupant load?

It is calculated by the designer from code tables and reviewed by the authority. A posted sign shows the approved number.

Can occupant load be increased later?

Possibly, if exits and fixtures allow, but it needs review and may need construction.