Allowance

An allowance is a sum of money included in the contract price for an item whose details are not yet known, such as a finish, a fixture or a piece of equipment.

Allowance

What it means

Allowances cover items that are still to be chosen when the contract is signed. Common examples include flooring, light fixtures, hardware and specialty finishes. The contractor carries the amount in the price. When the item is selected, the final cost is compared with the allowance, and the difference adjusts the contract up or down.

An allowance is an estimate, not a guarantee.

Why it matters

Allowances can hide risk. If the amount is set too low to make the price look attractive, the owner pays the shortfall later. Owners should ask what each allowance is based on, and when decisions must be made so orders arrive on time.

Late selections can also delay the schedule, especially for special-order materials.

AllowancePHASE 1Site and leasePHASE 2Design and engineeringPHASE 3BuildPHASE 4OperateBUILD: TRADES ON THE PROJECTElectricalMechanical / HVACPlumbingLow voltage / securityInterior systemsCarpentry / millworkPainting / finishesDoors / hardwareSELF-PERFORMED BY HSM CREWS ON THIS TYPE OF WORK
How HSM delivers this work. Highlighted trades are self-performed by our own crews.

How HSM handles it

HSM sets allowances using real pricing, not wishful numbers, and tells you what the amount covers, including installation. We set a decision date for each item, based on lead time, so your selections do not hold up the work.

Our carpentry and millwork team, interior systems crew and electricians install most of the items covered by allowances, so we know what installation involves and can price it accurately. On projects with many specialty finishes and lighting fixtures, this makes a visible difference to budget accuracy.

We report allowance spending as the job goes.

What to plan for

Keep a list of every allowance in your contract with its decision date. When a selection is late, tell us, and we will explain what it does to the schedule.